Temporary ED Enabling Phase – Beginning January 12, 2026
Starting January 12, the Temporary Emergency Department Enabling Phase will begin. At that time, all foot traffic and patient drop-offs will shift to a new location using the newly constructed entrance and exit off Wayman Lane.
The parking lot along the Wayman Lane side was re-striped several weeks ago to support this change. A new drop-off location is now in place using the designated turnaround, as shown on the project map attached.
Upcoming Construction Activity
- At the new Main Entrance facing Main Street, crews will continue framing and enclosing exterior walls, along with roofing work. Some construction noise will continue in and around this area.
- The Emergency Department entrance will also experience intermittent noise related to ongoing work.
We appreciate your continued patience as this important work progresses and are grateful for the ongoing collaboration from everyone in the community. If you have questions or concerns, please don’t hesitate to reach out to media@mdihospital.org.